Post Office Curb Extension
The City received $250,000 from the Transportation Improvement Board (TIB) for Complete Streets. This grant funds street retrofits that provide access to all users: bicyclists, pedestrians, motorists and public transportation riders.
The work includes construction of a curb extension with ADA curb ramps, sidewalks, catch basins, stormwater pipe, and preparation for rain garden installation, all located on the northwest corner of Washington Street at the Harrison Street intersection. The work also includes sawcutting, the removal of asphalt and concrete, and asphalt patch.
SEE BELOW FOR THE STATUS UPDATES THAT OCCURRED THROUGHOUT THE PROJECT:
February 3, 2020
This project is complete. Associated striping will be installed when the road surface temperature is warmer, sometime in the Spring.
January 21, 2020
Asphalt was placed on Monday, January 20, 2020.
January 17, 2020
The focus this week was pouring concrete. Due to the weather, the project has been delayed. As part of the Post Office Curb Extension project, Lakeside Industries, Inc. will be paving at the intersection of Harrison Street and Washington Street on Monday, January 20, 2020. Paving will start around 8:45 am and continue until 10:30 am. Washington Street will be open for modified two-way traffic (one lane) with flaggers to guide drivers. Harrison Street will be closed at the post office driveway for approximately 4 hours, from 8 am until noon. All sidewalks will be open. The project hopes to be concluded by early next week.
January 10, 2020
The curb has been poured. Next up for this project is pouring the flat areas of the bulbout. This project is set to be completed a week later than originally anticipated, which will make the date of completion January 17.
January 3, 2020
The Contractor has completed demolition. Next week the Contractor will begin setting catch basins and the subgrade for the sidewalk.
The things you find during demo! The Contractor stumbled upon an abandoned pipe while clearing old sidewalk.
December 26, 2019
This project is scheduled to begin on Monday, December 30, 2019. Estimated date of completion is January 10, 2020.